MEPCO New Connection Demand Notice Fee 2026 Guide
Paying your official electricity demand notice is the critical step connecting new property developments, residential homes, and commercial units across South Punjab to the main power grid. Multan Electric Power Company issues this mandatory fee voucher after field technical staff inspect your premise wiring, transformer load availability, and service drop cable distance. Understanding the complete MEPCO New Connection Demand Notice Fee 2026 guidelines ensures property owners calculate security deposits correctly, avoid unauthorized agent surcharges, and complete bank payments on time. This comprehensive manual details official fee breakdown structures, online payment channels, verification workflows, demand notice validity extension procedures, and practical solutions to prevent connection delays.
What is a MEPCO Demand Notice?
A demand notice is an official legal and financial document issued by the sub-divisional office after approving a new electricity connection application. It details the exact cost required to connect your property to the regional distribution network.
Key purposes of the demand notice include:
- Equipment Purchase Authorization: Covers the cost of official digital single-phase or three-phase meters, service drop wires, and mounting accessories.
- Advance Security Deposit Collection: Acts as a refundable security deposit calculated according to the sanctioned kilowatt load requested by the applicant.
- Grid Infrastructure Reinforcement: Funds service line installation, pole extensions, or transformer upgrades if your property is located far from main distribution lines.
- Legal Proof of Connection Approval: Serves as official confirmation that your property wiring has passed technical scrutiny by sub-divisional linemen.
Paying this voucher within the stipulated deadline guarantees priority meter installation by local field staff.

Key Components of the Demand Notice Fee Breakdown
The total amount listed on your demand notice varies based on connection category, meter phase requirements, and service line length.
Standard cost components included in the voucher are:
- Meter Cost: The official price of the energy meter (Single Phase, Three Phase Digital, or Net-Metering Bidirectional unit).
- Security Deposit: Calculated per kilowatt (kW) of sanctioned load to cover potential future bill defaults.
- Service Drop Line Charges: Cost of overhead service wire (up to standard length limits) connecting the main street pole to your building’s main switchboard.
- Testing and Administrative Fees: Official processing fees for meter calibration, testing lab certification, and central account setup.
- Transformer Cost Share (For High Load/Commercial): Applied if commercial premises or housing schemes require dedicated transformer installations.
Reviewing these individual line items ensures you pay only official regulatory charges without unverified overcharges.
Read More About MEPCO Defective Meter Replacement Application 2026
How to Pay Your Demand Notice Online and Offline
Multan Electric Power Company provides multiple convenient payment channels so applicants can clear their vouchers without long bank queues.
Available payment methods include:
- Designated Commercial Bank Branches: Pay directly over the counter at authorized branches of ABL, HBL, UBL, NBP, or Bank Alfalah by presenting the original printed demand notice voucher.
- Mobile Banking Applications: Enter the unique 14-digit bill reference number or consumer ID on your bank’s mobile app to pay electronically.
- JazzCash and EasyPaisa Mobile Wallets: Navigate to utility bill payments, select electricity provider, scan or enter the voucher ID, and complete payment via wallet balance.
- Post Office Counters: Designated regional post offices accept physical demand notice cash payments during standard operating hours.
Always retain the stamped bank receipt or save the digital transaction PDF after completing payment.
Read More About MEPCO Agricultural Tube Well Bill 2026 Guide
Step-by-Step Workflow After Demand Notice Payment
Clearing your payment triggers specific field work orders that lead directly to physical meter installation at your property.
Follow these post-payment verification steps:
Step 1: Submit Paid Receipt to SDO Office
Take a clear copy of the paid demand notice receipt along with your original application tracking folder to your local Sub-Divisional Officer (SDO).
Step 2: Store Purchase and Material Issuance
The sub-divisional store issues the approved meter, service drop wire, and connection seals to the assigned field line superintendent.
Step 3: Wiring Test Report Verification
Submit the finalized wiring test report completed by a licensed electrical contractor confirming internal distribution safety.
Step 4: Physical Meter Installation
Field linemen visit your property, mount the meter box on the exterior wall, connect overhead service drop wires, and activate the power connection.
Step 5: Master Billing Record Registration
The installed meter serial number and initial zero reading are entered into the central computer system to start regular monthly billing.
Adhering to the official MEPCO New Connection Demand Notice Fee 2026 procedure ensures your installation file moves rapidly through sub-divisional channels without administrative holds.
Extending Expired Demand Notice Validity
Demand notices come with a strict validity period, usually 30 days from the date of issuance. If payment is delayed past the due date, specific extension protocols apply.
Manage expired demand notice vouchers using these guidelines:
- Reason for Expiration: Failure to pay within 30 days invalidates the voucher, requiring official re-validation before banks accept payment.
- SDO Re-Validation Process: Visit the sub-divisional office with your original expired notice to request a date extension stamp and signature from the SDO.
- Revised Rate Adjustments: If utility tariffs or meter hardware prices increase during the expired period, a revised demand notice with differential charges may be issued.
- Application Cancellation Risk: Delaying payment beyond 90 days without official extension approval can lead to cancellation of your original connection application file.
Promptly extending expired notices prevents application cancellation and avoids re-filing paperwork from scratch.